How to Track Certificate of Occupancy Closeout in COINS ERP+

Certificate of occupancy (CO) closeout is the last stretch of a project: every authority inspection and sign-off that stands between substantial completion and a legal right to occupy the building has to be tracked, chased and cleared. If one inspection or correction is missed, turnover slips.

This guide follows a recorded closeout in COINS ERP+ Project Management for a fire alarm upgrade project: creating a CO inspection task list, assigning the authority sign-off tasks, watching Open Items as the critical path, logging and closing a Fire Marshal correction as a punch issue, closing the sign-off tasks, and uploading the signed certificate to the project documents.

  • Who does itProject manager or project engineer responsible for closeout
  • How oftenPer project, from substantial completion until the certificate is issued
  • Steps10 steps · 1 systems

Watch the full workflow

every click in this recording is an AI agent — no one is touching the keyboard.

In the recording, an AI agent signs in to COINS ERP+, selects project 120023 CVWRF Fire Alarm Upgrade and creates a CO-Insp task list for Certificate of Occupancy closeout inspections. It adds two authority tasks (Building Department final inspection sign-off and Fire Marshal / Life Safety final acceptance), confirms them in Open Items, then logs a Fire Marshal correction for an emergency lighting battery backup failure as a punch-list issue. It closes the issue, closes both sign-off tasks with a completion date, confirms Open Items is empty and uploads the certificate of occupancy PDF to the project documents.

  1. 1:20Sign in and open the working project
  2. 2:05Create the CO inspection task list
  3. 2:40Add one task per authority sign-off
  4. 3:20Review Open Items as the critical path
  5. 3:45Did an authority raise a correction?
  6. 4:00Log the correction as a punch-list issue
  7. 5:00Close the issue once the correction is cleared
  8. 5:15Close the authority sign-off tasks
  9. 5:30Is Open Items clear?
  10. 5:45Upload the certificate to project documents

Systems involved

You need access to each of these before you start. In the recording the agent works in all of them from one desktop, signed in as the user.

  • COINS ERP+Project Management module: task lists, tasks, issues, Open Items and project document upload

What you start with

  • Project record in COINS (project number and name)
  • List of authority inspections required for occupancy
  • Inspection results and correction notices from the authorities
  • Signed certificate of occupancy PDF

What you end with

  • CO-Insp task list with one task per authority sign-off
  • Punch-list issue for each correction, closed with dates
  • Closed sign-off tasks with completion dates
  • Certificate of occupancy filed in the project documents

Step-by-step: how to do it

  1. Action · COINS ERP+ · 1:20 in the video

    Sign in and open the working project

    Log in to COINS ERP+, expand Project Management in the menu and open Jobs or Select Working Project. Pick the project that is in closeout so every list and document you touch is filed against it.

    In the video
    Project number
    120023
    Project
    CVWRF Fire Alarm Upgrade
  2. Action · COINS ERP+ · 2:05 in the video

    Create the CO inspection task list

    On the project, open Lists > Task Lists and add a new task list for closeout. Give it a short code and a description that says exactly what it tracks, so it can be filtered later.

    In the video
    Task list
    CO-Insp
    Description
    Certificate of Occupancy Closeout Inspections
  3. Action · COINS ERP+ · 2:40 in the video

    Add one task per authority sign-off

    Open Lists > Tasks, choose the new task list and add a task for each inspection or acceptance an authority must give. Set status Open, the responsible person, a due date before the occupancy target and importance; leave the completed date blank.

    In the video

    Two authority tasks created on the CO-Insp list.

    • TASK0003 · Building Department Final Inspection Sign-Off O-Open
      Assigned to
      Project manager
      Due
      09/30/26
      Importance
      H-High
    • TASK0004 · Fire Marshal / Life Safety Final Acceptance O-Open
      Assigned to
      Project manager
      Due
      09/30/26
      Importance
      H-High
  4. Action · COINS ERP+ · 3:20 in the video

    Review Open Items as the critical path

    Go to the project's Open Items tab. Everything still open against the project appears here in one list, so this is the view to check before reporting progress toward occupancy.

    In the video

    Open Items lists TASK0003 and TASK0004, both High importance and due 09/30/26.

  5. Decision · COINS ERP+ · 3:45 in the video

    Did an authority raise a correction?

    Read the inspection result for each authority. A failed item or correction notice must be tracked as its own issue so it can be assigned and closed, not buried in a task note.

    • If yes Log it as a punch-list issue (next step) and keep the related sign-off task open.
    • If no Move straight to closing the sign-off task.
    In the video

    Fire Marshal correction: emergency lighting battery backup fail.

  6. Action · COINS ERP+ · 4:00 in the video

    Log the correction as a punch-list issue

    Open the Issues tab and add a new issue. Write a subject that names the authority and the deficiency, set the responsible party, status Open, type PUN-Punch List, importance and a due date.

    In the video
    Issue
    ISS0002
    Subject
    Fire Marshal Inspection Correction - Emergency Lighting battery backup fail
    Type
    PUN-Punch List
    Importance
    H-High
    Opened
    09/28/26
    • Responsible party: project manager
  7. Action · COINS ERP+ · 5:00 in the video

    Close the issue once the correction is cleared

    When the correction is verified, open the issue's details, change Status to C-Closed and confirm the closed date is recorded, then save. Open Items should now show the issue as gone.

    In the video
    Issue
    ISS0002
    Status
    C-Closed
    Impact
    3-No Impact
    Closed
    09/28/26
  8. Action · COINS ERP+ · 5:15 in the video

    Close the authority sign-off tasks

    Open each task's details, set Status to C-Closed and enter the Date Completed from the signed approval. Save each task.

    In the video

    Task details after closing.

    • TASK0003 · Building Department Final Inspection Sign-Off C-Closed
      Date completed
      09/28/26
    • TASK0004 · Fire Marshal / Life Safety Final Acceptance C-Closed
  9. Decision · COINS ERP+ · 5:30 in the video

    Is Open Items clear?

    Return to Open Items. Anything still listed is a blocker to turnover and needs an owner and a date before you file the certificate.

    • If yes File the certificate of occupancy.
    • If no Chase the remaining items before closing out.
    In the video

    Open Items shows no remaining records.

  10. Action · COINS ERP+ · 5:45 in the video

    Upload the certificate to project documents

    Open Files > Upload Project Documents, choose the signed certificate file and give it a clear description, then save so it is part of the permanent project record.

    In the video
    Document
    Certificate_o_ccupancy.pdf
    Description
    Certificate of Occupancy - Final Sign-Off & Permit

Rules, exceptions and controls

Rules to follow

  • Every authority inspection or acceptance required for occupancy gets its own task on the CO-Insp task list.
  • Corrections from an inspection are logged as Issues with type PUN-Punch List, not as notes on the task.
  • A sign-off task is closed only with a Date Completed taken from the authority's approval.
  • Open Items must be empty before the certificate is filed and the project handed over.
  • The signed certificate is stored in the project documents with a descriptive name.

When something doesn't match

  • An inspection fails or a correction is issued: log a punch-list issue, assign it and keep the sign-off task open until it clears.
  • A sign-off date is approaching with items still open: escalate only the items on the critical path to occupancy.
  • The certificate arrives without all tasks closed: confirm each authority approval before closing tasks retroactively.

Controls and audit trail

  • Task list and issues sit on the project record, giving an auditable trail of every sign-off.
  • Status changes (Open to Closed) are dated in the task and issue records.
  • Open Items acts as the single check that nothing is outstanding before turnover.
  • The final certificate is filed in the project document register for turnover and warranty.

Practitioner tips

  • Name task lists with a short prefix such as CO-Insp so closeout lists are easy to filter across projects.
  • Set task due dates a few days ahead of the occupancy target to leave room for re-inspection.
  • Write issue subjects as 'authority - deficiency' so a reader knows who raised it and what to fix.
  • Check Open Items, not just the task list, because issues and tasks both appear there.

About this recording

In the recording, the agent handled the closeout end to end in COINS ERP+: task list, sign-off tasks, punch issue, closures and the certificate upload.

Documented the way you'd train a new hire — and the same way an agent learns it.

See it on your workflow

Frequently asked questions

How do I track certificate of occupancy inspections in COINS?

Create a task list for closeout inspections on the project, add one task per authority sign-off with due dates, and watch the project's Open Items tab. Close each task with a completion date once the authority approves.

How do I log an inspection correction in COINS ERP+?

Open the project's Issues tab and add an issue with the authority and deficiency in the subject, type PUN-Punch List, a responsible party and a due date. Close it with C-Closed once the correction is verified.

Where do I store the certificate of occupancy in COINS?

Use Files > Upload Project Documents on the project, choose the signed PDF and give it a descriptive name so it is part of the permanent project record.

What blocks a certificate of occupancy?

Any authority inspection that has not been signed off and any open correction from those inspections. In COINS these show as open tasks and issues on the Open Items tab.

Can an AI agent do certificate of occupancy closeout in COINS?

Yes. As shown in the video, the agent works the same COINS screens a person does: building the task list, logging and closing the punch issue, closing sign-offs and uploading the certificate, with a person reviewing where needed.