WIP Schedule

a monthly report that compares each open contract's earned revenue with its billings to show which jobs are overbilled or underbilled

The job in one minute

What it produces

The monthly WIP schedule, a fade report, answered flags, a drafted adjusting entry and a WIP-to-ledger reconciliation.

Who owns it

The project accountant builds it, PMs own their estimates, the controller approves, the CFO decides what goes to the surety and the bank.

How often

Monthly for the schedule and entry, daily or weekly for the reconciliation.

Why it hurts

Estimates to complete arrive late, or unchanged on a job that clearly moved. A big subcontract is signed but not entered, so the forecast looks safe. A change still in negotiation sits in contract value. Delivered switchgear pushes percent complete ahead of the work. The schedule gets rebuilt in Excel from four exports, the entry is keyed by hand, and the ledger tie-out finds the problem on day twelve. Underbillings on nearly finished jobs are exactly what sureties disallow.

Systems it touches

The ERP, PM estimate workbooks in Excel, Outlook, SharePoint, Primavera P6 or Microsoft Project, Power BI, and Procore or Unifier.

If your ERP already posts the over and under billing entry from its own WIP, keep it. The agent checks the inputs that report cannot see before the numbers are computed.

  • ERP
  • PM estimate workbooks in Excel
  • Outlook
  • SharePoint
  • Primavera P6 or Microsoft Project
  • Power BI
  • Procore or Unifier

12 steps · 6 actions · 4 decisions · 2 human reviews

The workflow, step by step

Action Decision Human review Select a step in the flowchart to jump to it.

Related recordingJob cost reconciliation in Sage 300 CRE
Show the flowchart
  1. Decision · Agent

    After the cost cutoff, check for unposted payroll, AP, equipment and job cost batches. Any batch carrying job cost for the period stops the run for accounting.

  2. Action · Agent

    Pull every open job's contract value with approved changes, billed to date, cost to date, committed cost and last month's estimate.

  3. Action · ERP

    Collect each PM's estimate to complete from the ERP or the PM's own workbook.

  4. Decision · Agent

    The estimate is at least cost to date plus open commitments, an estimate unchanged for two months flags, uninstalled materials and pending changes stay out.

  5. Action · Agent

    Compute percent complete, earned revenue, over or under billing, gross profit and fade.

  6. Decision · Agent

    Fade past the threshold needs a PM explanation, an underbilling past 90 percent complete needs a reason and collection date, a projected loss goes to the controller.

  7. Human review · Controller

    PMs answer each flag in writing; the controller reviews the schedule.

  8. Action · Agent

    Draft the over and under billing entries and any loss provision, unposted.

  9. Human review · Controller

    The controller approves and the entry posts.

  10. Action · Agent

    Reconcile WIP to the ledger: cost, billings, contract asset and liability, retainage.

  11. Decision · Agent

    Every difference is zero or listed with its source transaction.

  12. Action · Agent

    Publish the package and keep the month's snapshot.

✓ Done

Rules vs judgment

  1. Exact rules

    • Every WIP formula, the cutoff check, the estimate floor, fade and late-stage underbilling thresholds, the to-the-cent ledger tie-out.
  2. The model reads

    • PM workbooks in their own layouts, PM explanations, signed subcontracts sitting in email, change status notes, surety and bank definitions. A rule still decides.
  3. A person decides

    • The estimate to complete, whether unpriced changes or delivered materials count, loss provisions, and what to tell the surety and the bank.

When it stops

  • Unposted batch at cutoff

    The run stops for accounting.

    run stops
  • PM workbook missing

    Last month's estimate carries, clearly marked stale.

    flagged
  • Committed cost above the estimate

    The PM revises or names the commitment that will be cancelled.

    routed
  • Signed subcontract found only in email

    Purchasing and the PM are flagged before the floor is tested.

    run stops
  • Export cut off at a row limit

    Totals are checked against the report footer and a mismatch stops the run.

    flagged
  • Reconciling difference with no source

    Stays on the list until a person finds the transaction.

    routed

What you end up with

A WIP package the controller can review in one sitting: every figure one click from the ERP screen it came from, every flag answered in writing, the entry drafted and ready, and a ledger tie-out that holds. The CFO gets a schedule the surety will not pick apart. Product →

Questions

Can the agent estimate cost to complete?

No. It tests the PM's estimate against cost, commitments, last month and the PM's own history. The number is the PM's.

Does it only support cost-to-cost?

Cost-to-cost is the default. A job-level table can set a different measure for a job whose contract calls for it.

Why reconcile weekly?

A difference found in week two has one or two transactions behind it. At month-end it has thirty.

Can it prepare the package for the surety or bank?

It lays the approved schedule into each one's format. What to send and how to explain it stays with the CFO. Invoice Coding to Job Cost →